The video above shows a software we call: MULTI PROGRESSED UPDATE TO UPDATE RELATIONSHIP CHECKER.
The software, in the above instance, runs through 12 updates each containing approximately 86,000 relationships. It checks the differences between each update backwards to the BASELINE and provides a report of all changes in 37.35 seconds.
The software extracts the data direct from the P6 database via SQL. The table data is then modified and formatted to provide ACTIVITY RELATIONSHIP tables that contain: ACTIVITY PREDECESSOR, ACTIVITY SUCCESSOR, RELATIONSHIP TYPE (FS,SS,FF & SF, LAGS and also other data.
Each table contains progress update data extracted from the P6 SQL database required to be able to undertake the DYNAMIC versus the AS-PLANNED v AS-BUILT DELAY ANALYSIS CALCULATOR delay analysis (see the video on the right).
A further software called: MULTI PROGRESSED UPDTAE TO UDATE AS-BUILT OUT OF SEQUENCE LOGIC CHECKER tells you in a matter of seconds exactly which activities commenced and finished out sequence compared to how they had been planned to be logically constructed.